Restoration News (Option B)

Restoration Project Tracker

Tewksbury Township Public Library · Oldwick, New Jersey

Last updated 25 Aug 2026

Stage 2 of 6 — Bids evaluated & contract awarded In progress
Complete In progress Upcoming
Building status Open Regular hours
Closing Early Oct 2026 Approaching
Closure length 4–6 months
Temporary location 18 Miller Ave

Overview

Scope of work

The Tewksbury Township Public Library restoration project is underway, with the goals of preserving the building’s history and architecture, making necessary repairs and updates, and enhancing the library’s functionality. The work includes:

  • Addressing the serious deficiencies in the building’s support structure.
  • Supplementing the inadequate vertical framing members and lintel over the west wall bank of windows.
  • Restoring the historic foyer and first floor library room with new wood flooring, paint, and light fixtures appropriate to the architecture.
  • Improving electrical, mechanical, and computer systems.
  • Regrading the property to minimize water damage to the building foundation.

Milestones

Schedule

Early Sept 2026
Engineering completed, bids solicited
Late Sept 2026
Bids evaluated, contract awarded
Early Oct 2026
Permitting complete, library closed and moved
Mid Oct 2026
Construction team on site, restoration begins
Feb–Apr 2027
Restoration completed, site cleaned up
Mar–May 2027
Furnishings returned, library reopens

Activity

Update log

Bidding

Design documents finalized, bids expected in September

Connolly & Hickey Historical Architects have qualified several potential construction firms and are finalizing the design and contract documents that will be included in the request to bid the project. We expect to receive bids and select a contractor in September 2026.

The Library Board has signed and returned the New Jersey Historic Trust grant agreement and is awaiting final approval of the paperwork, which is necessary before construction can start. We expect construction to begin in October 2026.

During the closure

Service continuity

Once construction commences, the library will be closed to the public for four to six months. Limited in-person service will be available just down the street at the Christian Education Building in Oldwick.

Christian Education Building 18 Miller Avenue, Oldwick, NJ 08858 9-minute walk from the library · 0.4 miles
What is available at the temporary location
Service Availability
Books & media Limited selection of new books and DVDs for adult, teen, and children’s collections. Most of the collection will be in storage; inter-library loan remains available.
Holds & pick-ups Browse the Hunterdon County catalog, request from the full MAIN system, and collect holds at the temporary location.
Printing Black-and-white and color printing, plus a copier-scanner.
Wi-Fi Public Wi-Fi for guests bringing their own devices.
Storytime Continues outdoors at the new location until late October. Other community groups cannot be accommodated.
Map showing the walking route from Tewksbury Township Library on Old Turnpike Road to the Christian Education Building at 18 Miller Avenue, a 9-minute walk of about 0.4 miles.
Walking route to the temporary location.

Documentation

Site photographs

Photo
Exterior before restoration — Aug 2026
Photo
Structural conditions in the basement — Aug 2026
Photo
West wall window bank — Aug 2026
Photo
Temporary location at 18 Miller Ave

Reference

Published timeline

Tewksbury Library Restoration Project timeline, September 2026. Early September 2026: engineering completed and bids solicited. Late September 2026: bids evaluated, terms negotiated, and construction contract awarded. Early October 2026: permitting completed, library closed and moved to temporary location. Mid October 2026: construction team on site and restoration begun. February to April 2027: restoration completed and site cleaned up. March to May 2027: materials and furnishings returned and library reopened.
Board-issued timeline, September 2026. Scroll sideways on a small screen.

Questions

Common questions

When will the library close?
Early October 2026, once permitting is complete and the construction contract is in place. The exact date will be posted here.
How long will it be closed?
Four to six months. Restoration is projected to finish between February and April 2027, with reopening between March and May 2027.
Where do I go while it is closed?
The Christian Education Building, 18 Miller Avenue in Oldwick — a 9-minute walk from the library.
Can I still borrow and return books?
Yes. A limited new-title selection is on hand, and anything in the Hunterdon County catalog or wider MAIN system can be requested and collected at the temporary location.
Will Storytime continue?
Yes, outdoors at the temporary location until late October.
How do I get project news?
This page is updated as each stage completes, and updates also run in the monthly newsletter.

Contact

Ask the Library Board

The Library Board will continue to share updates as the project moves forward. We appreciate our patrons’ patience and understanding as this essential work gets under way.

[email protected]  ·  908-439-3761

Funded in part by a $430,213 matching grant from the New Jersey Historic Trust. Phase 3 — interior furnishings, shelving, finishes, lighting, and technology — is still being funded.